By Sandeep Pawar, Broker, RE/MAX Gold Realty Inc., Brokerage
Short answer
A new freehold home in Ontario is sold with either a firm closing date or a tentative closing date. A firm date is fixed from the start. A tentative date can be pushed back twice by the builder, by up to 120 days each time, with at least 90 days' written notice and no compensation. After that, the builder must set a firm closing date. If the builder misses the firm date, you are generally owed delayed closing compensation. These rules come from the Tarion addendum attached to every new freehold agreement.
The key dates in your agreement
| Date | What it means | | --- | --- | | First Tentative Closing Date | The builder's first estimate when construction has not started or is early | | Second Tentative Closing Date | Up to 120 days after the first, if the builder extends | | Firm Closing Date | No later than 240 days after the First Tentative Closing Date | | Outside Closing Date | The last possible closing date: 365 days after the earlier of the Second Tentative or Firm Closing Date | | Purchaser's Termination Period | 30 days after the Outside Closing Date to cancel if the home is still not ready |
Notice rules
- To move a tentative date, the builder must give written notice at least 90 days before the current date. If it does not, that date becomes the firm closing date.
- Any change to a firm closing date also needs at least 90 days' written notice.
- If the builder fails to give 10 days' notice of a delay, extra compensation can apply.
- All dates must be specific calendar dates on business days, not "floating" dates.
When a delay is not compensated
Builders can extend dates without compensation for "unavoidable delays" such as strikes, fire, floods or similar events outside their control, as long as they give written notice when the delay starts and when it ends.
What delayed closing compensation looks like
If the builder closes after the firm date, Tarion's published rules allow total compensation of up to $7,500, including a fixed $150 per day for living expenses and receipted costs such as moving and storage. I explain the claim process in a separate article on delayed closing compensation.
Condos are different
Condo agreements use an "occupancy date" system rather than closing dates, with interim occupancy before final closing. The rules for delayed occupancy follow a similar idea but have their own dates and notices.
My advice
- Read the Statement of Critical Dates on the first page of the Tarion addendum before you sign.
- Plan your housing around the Outside Closing Date, not the first tentative date.
- Keep every notice the builder sends, with the date you received it.