By Sandeep Pawar, Broker, RE/MAX Gold Realty Inc., Brokerage
Short answer
If your builder closes after the firm closing date, or fails to give proper notice of a delay, you can usually claim delayed closing compensation. Under Tarion's published rules for freehold homes, the total is up to $7,500. It includes a fixed $150 per day for living expenses, with no receipts needed, plus receipted costs such as moving and storage. You first claim from the builder within 180 days of closing, and if the builder does not pay, you claim through Tarion.
When you are entitled to compensation
- The home closes after the firm closing date (or after a date that became firm because notice was missed)
- The builder did not give 10 days' notice of a delay
- You terminate the agreement because the home is not finished by the outside closing date
You are generally not compensated for delays caused by "unavoidable delay" events, such as strikes, fire or natural disasters, where the builder followed the notice rules. I explain the different dates in Tentative vs firm closing dates.
What is paid
| Item | How it works | | --- | --- | | Living expenses | A fixed $150 per day of delay, no receipts required | | Other direct costs | Moving, storage and similar costs, with receipts | | Late notice | $1,500 if the builder fails to give 10 days' notice ($150 x 10 days) | | Total limit | Up to $7,500 |
If you terminate because the home is not complete by the outside closing date, you are entitled to a full refund of the money you paid, plus interest, in addition to compensation.
How to claim
- Keep records: every notice from the builder, rent or hotel receipts, moving and storage bills.
- Claim from the builder within 180 days of closing (or of termination). Your lawyer can request it as an adjustment on closing.
- If unpaid or disputed, file a claim with Tarion during the first year of possession, or within 365 days after termination, using the delayed closing claim form on MyHome.
Condo buyers
Condo agreements use occupancy dates rather than closing dates. Delayed occupancy compensation works on the same idea, measured against the condo occupancy dates in your agreement. Keep the same records.
Tips from my files
- Many buyers forget to claim. Put a reminder in your calendar on closing day.
- Ask your lawyer to include compensation as a credit on the statement of adjustments where the builder agrees.
- Do not sign a release or amendment that waives your compensation without legal advice.